Western Sydney Industrial Estate

Kemps Creek, NSW

Western Sydney Industrial Estate: bulk earthwork, site preparation, drainage & stormwater on site in Kemps Creek
Year
2024
Duration
9 months
Volume
120,000 m³
Length
1.8 km

01

The problem

A 32-hectare greenfield lot sat on reactive clay with a 6 m fall across the site. Pad levels had to be locked before warehouse slabs could be poured, with no room for re-work on the program.

02

The solution

We staged cut-to-fill in four cells, moisture-conditioned the clay on site and compacted in 200 mm lifts under Level 1 supervision. GPS machine control held every pad to design, and temporary sediment basins went in before the first cut.

03

The result

Four pads handed over flat and certified, with zero imported fill. Stormwater trunk and basins commissioned before the builder mobilised.