SampleIndustrial Estate · NSW
Western Sydney Industrial Estate
Kemps Creek, NSW

- Year
- 2024
- Duration
- 9 months
- Volume
- 120,000 m³
- Length
- 1.8 km
01
The problem
A 32-hectare greenfield lot sat on reactive clay with a 6 m fall across the site. Pad levels had to be locked before warehouse slabs could be poured, with no room for re-work on the program.
02
The solution
We staged cut-to-fill in four cells, moisture-conditioned the clay on site and compacted in 200 mm lifts under Level 1 supervision. GPS machine control held every pad to design, and temporary sediment basins went in before the first cut.
03
The result
Four pads handed over flat and certified, with zero imported fill. Stormwater trunk and basins commissioned before the builder mobilised.