SampleSubdivision · QLD
Sunshine Coast Subdivision
Palmview, QLD

- Year
- 2023
- Duration
- 11 months
- Volume
- 85,000 m³
- Length
- 4.2 km
01
The problem
A 180-lot stage on low-lying ground with a high water table and wet-season deadlines. Sewer, water and stormwater had to be in and tested before roadworks.
02
The solution
We lifted lot levels with engineered fill, dewatered trench runs ahead of pipe crews and sequenced sewer, water and stormwater in shared corridors. Every run was CCTV'd and pressure-tested before backfill.
03
The result
All 180 lots serviced and signed off by the water authority first inspection. Stage handed to roadworks two weeks early.